The Maltby Colliery winding tower toppling during a controlled explosive demolition

Maltby Colliery

A carefully sequenced demolition and material recovery project at one of South Yorkshire’s historic deep mines.

Explosive charges firing at the base of the Maltby Colliery winding tower

Industrial · Maltby, Rotherham

Project overview

Demex undertook the demolition of the surface structures at Maltby Colliery, including the headframe, washery and screening buildings, and extensive conveyor systems.

Unlike a conventional building, a colliery’s surface infrastructure is a complex network of heavy steelwork, machinery and processing facilities. Its scale and structural character are closer to an industrial steelworks, requiring a demolition sequence designed around both safety and the practical handling and recovery of materials.

On site

The job on film

On site

Demolition of the surface structures at Maltby Colliery.

In detail

How the job ran

A landmark in South Yorkshire’s mining history

Maltby Colliery was developed in the early 20th century as part of the region’s deep-coal industry. For generations, the mine and its associated surface buildings formed a defining feature of the local landscape and supported the surrounding community. The colliery closed in 2013, bringing to an end more than a century of mining activity at the site.

The demolition marked a significant change for a site with a long industrial history, requiring an approach suited to its large-scale infrastructure and varied materials.

Planned demolition

Demex dismantled the surface structures in a carefully planned sequence. The order of works was designed to ensure that the heaviest steel could be removed while sufficient space remained for safe handling and processing, rather than becoming difficult to access as the site was progressively cleared.

Material recovery

Recovered steel was processed through the group, while masonry and concrete were crushed on site. This approach supported efficient material management and helped reduce the amount of material requiring off-site disposal.

By combining an engineered demolition sequence with considered material recovery, Demex managed the challenges of dismantling a complex industrial site while helping prepare the former colliery for its next chapter.