Aviation
Project overview
Leeds Bradford Airport is undertaking a major redevelopment programme that includes a terminal extension and the refurbishment of existing facilities. The first phase, a three-storey terminal extension, was completed in summer 2025.
Demex Northern is carrying out the refurbishment of the existing terminal in six phases. Phases 1 and 2 were completed by spring 2026, with the remaining works scheduled to take place in late 2026 and completion expected in early 2027.
By the numbers
Leeds Bradford Airport in figures
Airport redevelopment programme
Phases of terminal refurbishment
Phases completed by spring 2026
Expected completion
In detail
How the job runs
The challenge
Working in a busy, operational airport requires careful planning and coordination. The works involve complex demolition and structural alterations within an environment subject to strict safety, security and access requirements.
Our work
The scope of work has included:
- Soft strip of existing terminal areas
- Formation of new openings in structural slabs using robotic rigs
- Demolition of the airside international baggage reclaim building and passenger walkway
- Removal of multiple lifts, staircases and escalators
The phased approach enables the refurbishment to progress in a controlled sequence within the live airport environment.
Safety and security
Before starting work, all Demex Northern staff were DBS-vetted, completed GSAT training and obtained the required airside clearance passes. These measures supported compliance with the airport’s security and access requirements throughout the project.
Project status
With the first two refurbishment phases complete, Demex Northern is progressing the remaining works as part of the wider redevelopment programme.